Land Transport Authority · CREG EPB TBM · Ø6.6 m
Circle Line Stage 6 closed the final gap in Singapore's orbital MRT line, connecting HarbourFront to Marina Bay. Contract C882 deployed four 6.6-metre CREG earth-pressure-balance machines on twin-bore drives beneath some of the island's densest urban fabric.
Our team members served on the contract, handling machine assembly, production tunnelling and end-of-drive dismantling — often recovering machines in tight underground chambers where every lift had to be planned to the centimetre.