Overview

Not every tunnel carries trains. Singapore's EW2 cable tunnel — driven with a Kawasaki slurry machine — carries the transmission lines that power the island, while in Qatar a compact 3.5-metre Herrenknecht TBM drove utility bores beneath Doha.

Small-diameter tunnelling concentrates every challenge into less space: tighter logistics, harder interventions, less room for error. Our director Mohammad Zahirul Islam brought these drives home safely.

Scope of Works

  • Small-diameter slurry and EPB TBM operation
  • Confined-space logistics and interventions
  • Utility tunnel finishing works
  • Machine recovery from tight reception shafts

Gallery

More from our track record

Japan / Bangladesh Japanese Utility Tunnels & Bangladesh Civil Works
Public infrastructure owners
Japanese Utility Tunnels & Bangladesh Civil Works
Various
View Details ↗
Singapore Thomson–East Coast Line — T202
Land Transport Authority
Thomson–East Coast Line — T202
Kawasaki TBM · Ø6.6 m
View Details ↗
Singapore Cross Island Line — CR110 / CR115
Land Transport Authority
Cross Island Line — CR110 / CR115
CREG EPB TBM · Ø12.6 m & Ø7.2 m
View Details ↗